Completed work
World Concrete engaged ALL CORE to support lease-end make-good works at a warehouse in Wetherill Park. The existing concrete slab needed to be cut and removed so a replacement slab could be installed. The team completed 750 linear metres of road sawing over two days and removed the cut concrete to prepare the area for the new slab. After the replacement concrete was placed, ALL CORE returned to complete soff-cut control joints, helping manage shrinkage and reduce uncontrolled cracking.
Project Results
- 750 linear metres of road sawing completed
- Road sawing delivered across two days
- Existing warehouse slab cut and removed for lease-end make-good works
- Area prepared for installation of the replacement concrete slab
- Soff-cut control joints completed after the new slab was placed